Canadian Natural Resources Limited utilized Pacesetter’s combined technologies of XPACE EM MWD and our modified Orbit RSS to successfully drill their fastest 171mm monobore in the Karr field. The record well was completed in less than 6.5 days from spud at 5,413m MD.
The 4,792m lateral was completed in a single run, drilling for 74.5 hours with an average ROP of 64.3m/hr.
Congratulations to CNRL and the rig crews of Horizon 48 for this great achievement.
OPERATOR Canadian Natural Resources Limited
HOLE SIZE 171mm
RUN DETAILS 612m MD to 5,413m MD
HIGHLIGHTS
TECHNOLOGIES

Pacesetter’s Orbit RSS breaks records drilling 4,964m in a single run Using Pacesetter’s combined technology of XPACE EM MWD and our modified PowerDrive Orbit RSS, Canadian Natural Resources Limited drilled the longest 159mm RSS run, and their deepest Falher well in the Sundance field. The 4,964m lateral was completed in a single run, drilling for […]
Read More
Fastest of 4 Montney wells in the Valhalla field drilled in less than 8 days Canadian Natural Resources Limited drilled their fastest Montney well in the Valhalla field by utilizing Pacesetter’s Redline Pulse MWD along with our High Speed and Performance motor. The single run 2,971m lateral was drilled at an average ROP of 63.6m/hr, […]
Read More