Using Pacesetter’s combined technologies of XPACE EM MWD, our modified PowerDrive Orbit RSS, and Montney High Performance motor, Velvet drilled their fastest laterals in the Montney field.
Congratulations to Velvet Energy Ltd., Ramdar Resource Management Ltd., and the rig crews of Savanna 639 on these impressive accomplishments.
OPERATOR Velvet Energy Ltd.
HOLE SIZE 159mm
1st LATERAL HIGHLIGHTS
METERS DRILLED 2,695m MD
CIRC HOURS 73 hrs
MAX ROP 115m/hr
AVERAGE ROP 52.8m/hr
2nd LATERAL HIGHLIGHTS
METERS DRILLED 2,706m MD
CIRC HOURS 75 hrs
MAX ROP 115m/hr
AVERAGE ROP 55.8m/hr
TECHNOLOGIES

Pacesetter’s modified Orbit RSS breaks records in the Pembina field Using Pacesetter’s combined technologies of XPACE EM MWD and our modified PowerDrive Orbit RSS, one Operator drilled 3 record wells in the Pembina field. The vertical and build sections on the final 2 wells were drilled while continuing on into the lateral reaching TD in […]
Read More
Pacesetter’s Orbit RSS breaks records drilling 4,964m in a single run Using Pacesetter’s combined technology of XPACE EM MWD and our modified PowerDrive Orbit RSS, Canadian Natural Resources Limited drilled the longest 159mm RSS run, and their deepest Falher well in the Sundance field. The 4,964m lateral was completed in a single run, drilling for […]
Read More