Record North Karr Montney Well for HHR

Hammerhead drills their fastest Montney well with conventional tools and XPACE DT MWD

Using Pacesetter’s XPACE Dual Telemetry MWD platform, Hammerhead successfully drilled their fastest Montney well in the North Karr field to date reaching TD at 5,771m MD in 10 days from spud.

Congratulations to Hammerhead Resources Inc, Ramdar Resource Management Ltd, and the rig crews of Stampede 6 for this impressive accomplishment.

MONTNEY

OPERATOR                Hammerhead Resources Inc.
HOLE SIZE                 171mm / 156mm
TOTAL DEPTH           5,771m MD

HIGHLIGHTS

  • Drilled 2,879m in a single run
  • Average lateral ROP of 42.8m/hr

TECHNOLOGY

  • XPACE DT MWD

 