Using Pacesetter’s combined technologies of XPACE EM MWD, our modified Pin Down PowerDrive Orbit RSS, and Montney High Performance motor, Velvet drilled their fastest well in the Montney field to date.
Completed in just over 6 days from Spud to TD, this pacesetter well was the final well on a record breaking pad.
Congratulations to Velvet Energy Ltd., Ramdar Resource Management Ltd., and the rig crews of Horizon 50 on this remarkable accomplishment.
OPERATOR Velvet Energy Ltd.
HOLE SIZE 311mm / 171mm / 159mm
RECORD WELL HIGHLIGHTS
TOTAL METERS 4,792m MD
TOTAL DRILL HRS 89 hrs
TOTAL CIRC HRS 25 hrs
AVERAGE ROP 54.0m/hr
PAD HIGHLIGHTS
TOTAL METERS 19,290m MD
TOTAL DRILL HRS 409 hrs
TOTAL CIRC HRS 124 hrs
AVERAGE ROP 47.2m/hr
TECHNOLOGIES

Pacesetter’s modified Orbit RSS breaks records in the Pembina field Using Pacesetter’s combined technologies of XPACE EM MWD and our modified PowerDrive Orbit RSS, one Operator drilled 3 record wells in the Pembina field. The vertical and build sections on the final 2 wells were drilled while continuing on into the lateral reaching TD in […]
Read More
Pacesetter’s Orbit RSS breaks records drilling 4,964m in a single run Using Pacesetter’s combined technology of XPACE EM MWD and our modified PowerDrive Orbit RSS, Canadian Natural Resources Limited drilled the longest 159mm RSS run, and their deepest Falher well in the Sundance field. The 4,964m lateral was completed in a single run, drilling for […]
Read More