Case Studies

Aspenleaf Drills Record 6700m Well

Conventionally drilled single run 4,596m lateral leads to Aspenleaf’s longest well in Leduc-Woodbend

Using Pacesetter’s Redline Pulse MWD and NBI motor, Aspenleaf successfully drilled their longest Nisku well in the Leduc-Woodbend field to date reaching TD at 6,700m MD. The collaboration between Aspenleaf’s Drilling and Geology groups along with Pacesetter’s Well Planning and Optimization groups made this an efficient well, meeting the goal of a single run lateral.

Congratulations to Aspenleaf Energy Limited and the rig crews of Savanna 638 on this impressive achievement. Thank you to Pacesetter DD Supervisors Jason Puddester, Dan Canavan & Joel Migowsky, and MWD Supervisor Taras Mykhaylyak.

NISKU

OPERATOR                Aspenleaf Energy Limited
HOLE SIZE                 311mm / 222mm / 159mm
RUN LENGTH            4,596m
TOTAL DEPTH           6,700m MD

HIGHLIGHTS

  • 4,596m drilled in a single run
  • Average lateral ROP of 56.4m/hr

TECHNOLOGIES

  • Redline Pulse MWD
  • Near Bit Inclination Motor

 

 

Download this Performance Highlight