Using Pacesetter’s combined technology of XPACE EM MWD and our modified PowerDrive Orbit RSS, Canadian Natural Resources Limited drilled the longest 159mm RSS run, and their deepest Falher well in the Sundance field.
The 4,964m lateral was completed in a single run, drilling for 115.5 hours with an average ROP of 44.1m/hr. The record well was completed in just over 8 days from spud at 5,586m MD.
Congratulations to CNRL and the rig crews of Horizon 48 for this incredible accomplishment.
OPERATOR Canadian Natural Resources Limited
HOLE SIZE 159mm
TOTAL DEPTH 622m MD to 5,586m MD
HIGHLIGHTS
TECHNOLOGIES

Pacesetter’s modified Orbit RSS breaks records in the Pembina field Using Pacesetter’s combined technologies of XPACE EM MWD and our modified PowerDrive Orbit RSS, one Operator drilled 3 record wells in the Pembina field. The vertical and build sections on the final 2 wells were drilled while continuing on into the lateral reaching TD in […]
Read More
Fastest of 4 Montney wells in the Valhalla field drilled in less than 8 days Canadian Natural Resources Limited drilled their fastest Montney well in the Valhalla field by utilizing Pacesetter’s Redline Pulse MWD along with our High Speed and Performance motor. The single run 2,971m lateral was drilled at an average ROP of 63.6m/hr, […]
Read More